Nonconformance Report
Scenario: An operator finds fasteners below the specified torque on an assembled unit; the report runs from raising to closure.
| # | Step | Owner | What happens |
|---|---|---|---|
| 1 | Raise the report | Assembly operator | Stop work on the unit, tag it, and complete the report: part number, serial, requirement breached, what was observed, and when. Hand the tagged unit to the supervisor. |
| 2 | Contain | Production supervisor | Quarantine the unit and all units built since the last good torque check. List the serials affected. Check whether any have shipped and tell quality immediately if so. |
| 3 | Triage and classify | Quality engineer | Classify as minor or major using the escalation test. Check the torque tool's calibration status; an out-of-calibration tool widens the containment scope and links to the calibration record. |
| 4 | Decide disposition | Material review group | Quality, engineering and production agree: rework (re-torque and re-inspect) or scrap. A use-as-is decision needs engineering justification in writing and quality approval. |
| 5 | Execute and verify | Production supervisor | Carry out the disposition, attach rework records, and have an inspector verify. Release quarantined units only after verification. |
| 6 | Close or escalate | Quality manager | Close if the cause is isolated and fixed. If the same defect appeared in the last quarter's reports, open a CAPA and link its number to this report. |