A month-end close is a sequence of dependent tasks with a hard calendar. This worked SOP orders the tasks by working day, names the owner of each, and shows where review and sign-off happen so books close the same way every month.

Template preview

Six-working-day month-end close

Copy it, download it as Markdown or CSV, or print it. It is a worked example: change the owners, steps and records to fit your process.

WORKED EXAMPLE

Month-End Close

Adapt before use

Scenario: A mid-sized company with a general ledger, bank accounts and a receivables ledger closes each month in working days one through six.

#StepOwnerWhat happens
1WD1: Cut off subledgersAccounts payable and receivable leadsPost all invoices dated in the month, then lock the periods. Record the lock time. Late items are posted to the next month with a note.
2WD2: Request and book accrualsFinance analystSend the accrual request to budget holders with a response deadline, then book goods received not invoiced and payroll accruals.
3WD3: Reconcile balance sheet accountsAccountantsPrepare bank, receivables, payables and prepayment reconciliations. Decision point: unreconciled differences above the threshold must be explained or adjusted.
4WD4: Review reconciliationsAssistant controllerA second person reviews each reconciliation and signs it. Preparer and reviewer must differ.
5WD5: Review the numbersFinancial controllerCompare actuals to budget and last month. Variances above the stated threshold need a written reason from the owning manager.
6WD6: Sign off and lockFinance directorApprove the close pack, lock the ledger, and file the signed checklist. Records kept: reconciliations, journals with approvals, variance notes, signed checklist.
Document owner: ______Approver: ______Version: ____Next review: ______
Guidance

When to use it, how to adapt it, what to avoid

Good practice

Subledgers must close before the general ledger, and accruals depend on cut-off decisions made days earlier. A close SOP is really a dependency map with owners attached.

Express timing in working days, such as WD1 to WD6, rather than dates. The same SOP then works for every month.

FAQs

Questions this page often raises

Short, direct answers. Open any question, or expand them all.

How many days should a close take?
It depends on your size, systems and reporting needs. Set a target based on what stakeholders actually need, then shorten it by removing the longest dependency chain first.
Should the close SOP be a checklist or a procedure?
Both. The procedure explains how each task is done and who reviews it. The checklist is the dated record for one month's close.
What about quarter-end and year-end?
Add extra tasks, such as depreciation review and audit schedules, as an appendix or sibling SOP rather than overloading the monthly version. The finance department page covers the wider rhythm.