Change Management
Scenario: An engineer wants to raise the connection pool limit on a production database to relieve slow requests during peak hours.
| # | Step | Owner | What happens |
|---|---|---|---|
| 1 | Raise the change request | Requesting engineer | Complete the request with scope, reason, test evidence from staging, risk and rollback plan. Incomplete requests are returned without review. |
| 2 | Classify the change | Change coordinator | Decide standard, normal or emergency. A database parameter in production is normal and goes to the review board. |
| 3 | Assess risk | Service owner and on-call lead | Check for clashes on the calendar and for dependent services. If the risk is high, require a smaller trial change first. |
| 4 | Approve or reject | Change advisory group | Approve for a named window, ask for more, or reject with a reason. Approvals are recorded in the request. |
| 5 | Implement in the window | Requesting engineer | Apply the change, watch the agreed metrics for the agreed time and trigger the rollback if they pass the threshold. The on-call lead is told when work starts and ends. |
| 6 | Close the record | Change coordinator | Record the outcome, whether rollback was used and lessons. Failed changes feed the next review of the procedure. |