Quality Inspection
Scenario: A small manufacturer inspects purchased castings on receipt and finished housings before dispatch.
| # | Step | Owner | What happens |
|---|---|---|---|
| 1 | Verify paperwork on receipt | Receiving clerk | Match the purchase order, delivery note and material certificate. Missing certificate means the lot goes to the hold shelf and the buyer is notified; it is not released to inspection. |
| 2 | Perform receiving inspection | Quality inspector | Draw the sample according to the plan for the lot size. Measure the three critical dimensions with calibrated gauges and check visual defects against the reference photos. Record each reading. |
| 3 | Decide accept or hold | Quality inspector | If any critical dimension fails, tag the lot Hold, move it to the red cage and raise a nonconformance report. Minor cosmetic issues are logged and escalated to the quality engineer. |
| 4 | Check first piece and in-process | Machine operator and inspector | After set-up, the operator measures the first piece and the inspector verifies it. Periodic checks at the interval in the control plan; trends toward a limit trigger an adjustment before parts go out of tolerance. |
| 5 | Run final inspection | Quality inspector | Inspect the finished lot to the final plan, including labeling and count. Compare readings with the drawing revision on the traveler. Sign and date the inspection record. |
| 6 | Release or disposition | Quality manager | Release lots that pass. For failed lots, record disposition: rework, scrap, use-as-is with customer concurrence, or return to supplier. Reinspect reworked lots at a tighter sample. |